Mark Moore, Independent Energy & Grid Infrastructure Adviser, explains why the grid connection queue overstates the likely impact of data centres and how heat pump installations can continue to grow, highlighting the importance of local grid capacity, connection reforms and thermal storage.
Anyone reading the energy press, or even the national press over the past few months could be forgiven for thinking that the electrical grid is full.
In July this year (2026) an Ofgem consultation quantified the queue of demand connections holding a contracted connection offer at over 125 GW as at June 2025. This was up from 41 GW only seven months earlier in November 2024.
Approximately 73 GW or 87% of that growth was for data centres.
To put that in perspective, peak electricity demand in Great Britain last year was only 45 GW. More than 1.6 times the country’s peak demand added to the queue for data centres alone in seven months.
If you are a heat pump installer, it would be quite reasonable to wonder where the power is coming from to connect your installations.
Luckily, the queue is the wrong number to worry about.
What will actually connect?
National Energy System Operator’s (NESO) ten-year outlook, published in Summer 2026, expects only about 8.7 GW of data centre capacity to be connected by 2036, drawing about 23.5 TWh annually. If the queue holds 73 GW of data centre applications, NESO expects only about one megawatt in eight to connect. In any case, NESO’s own stakeholders told it that nearly half of the pipeline may be wholly speculative or duplicated.
In addition, there’s a second factor to take into account. A data centre’s booked capacity is not it’s peak requirement. A site will book the full capacity for the whole campus even before the first hall is built, it will add headroom for cooling on the hottest possible day and almost always carry redundant power feeds. In short, the booked capacity is for safety and resilience, the develop never wants to hit that capacity.
UK Power Networks’ data on it’s existing data centre sites over three years show that data centres typically draw around 20% of the booked capacity. Almost half of the data centres never exceeded 40% at any point. Another study by NGED found enterprise sites only reached capacity for a part of the working day.
Applying that 20% draw to the smaller connection forecast, we come down to a 2036 projected total of around 15 TWh. Significantly smaller than the headlines suggest.
How big is the heat pump load?
We can now more realistically compare the heat pump load to the projected data centre load. There were a record number of heat pump installations in 2025, MCS certified just over 60,000. The warm homes plans sets a target of 450,000 a year by 2030.
If installations can reach that rate, and hold it, there will be about 4.3 million heat pumps in the UK by 2036. Using a average requirement of 3,500 to 4,000 KWh each, they will use about 15-17 TWh per year. On an evening in January with every heat pump running, the diversified peak will be between 6.5 and 8.7 GW. For details of how these estimates were calculated please take a look at the chart.
So, the two loads are about the same size: heat pumps around 15-17 TWh and data centres at 23.5 TWh but more likely to be 15 TWh. To put I another way, 8.7 GW of data centres against 6.5 – 8.7 GW of heat pump peak.
The data centre load that will connect is unlikely to be the monster that the queue suggests, and the power it’s going to draw will be smaller again.
A similar sized load to that the heat pump installers are building themselves.
Four routes to power
The two loads will connect to the network by different routes, for the heat pumps it depends on their size.
Route 1: A single 32 amp domestic heat pump is simply connect and notify within 28 days. There’s no application and no queue.
Route 2: Above 32 amps, or where there are several heat pumps going in together, the installer needs to apply first and waits, typically 45 days for an answer.
Route 3: An energy centre for a heat network is a different case. It’s heat pumps may require several megawatts, an application must be made to the DNO (Distribution Network Operator) like any other large customer. These schemes will join the demand queue. That particular queue grew from 24 GW to 28 GW between November 2024 and June 2025.
Data centres mostly go along Route 4, the transmission demand queue, which grew from 17 GW to 97 GW over the same period. The data centres are not competing with the domestic heat pumps for a low voltage feeder.
The important point is that all four routes meet up at the primary substations, it’s at these specific substations that the connecting figures matter, not the queued one in print.
There’s another key point. Nobody can track, or even see, all four routes at once. NESO told an FOI request last December that it holds no register of demand connections. Generation and storage are listed on the TEC register; I track that every week. There is no equivalent register for demand.
Connections reform: What it does and doesn’t do
Connections reform has, up to now, been all about generation and storage. By June 2026, NESO and the distribution companies had issued Gate 2 offers to 713 project, 37 GW in all.
Distribution connected demand sits outside that reformed process.
For demand, there is an attempt to start controlling the queue. Ofgem’s Curate proposals which are squarely aimed at a single type of load. Data centres would pay a commitment fee (or put a bond or guarantee in place) of £237,500 to £712,500 per MW. forfeited if they leave the queue before energisation. Separately, data centres from 10 MW would have to meet progress milestones or risk removal.
No doubt this will shrink the speculative queue further which is good news for everyone behind it, including larger heat pump installations. But this is a price mechanism and not a ranking, it’s effects rely on an ‘economically rational’ rational response from developers of queuing projects. From experience in renewable energy you can see that’s not guaranteed. Heat network zoning arrives in England this year, with the Warm Homes Plan expecting heat networks to supply 7% of heat by 2035, up from 3%. Every one of those energy centres will travel along connection route 3.
Ranking: Denmark did it, Finland is about to
The demand surge driven largely by data centres is a common feature across energy networks worldwide.
Denmark faced the same surge: 60 GW of demand requests against a national peak demand of 7GW with data centres accounting for 14GW of those requests. Energinet paused large connections on the 2nd of March.
On the 1st October a cross-party agreement replaced Denmark’s first-come first-served with four ranked categories which came into force very quickly on the 12th October: households and critical functions first, transport, heat and industry second, storage third and data centres last. In stark contrast to the current regulations in the UK, Energinet may also refuse storage and data centres outright where capacity will not exist in the foreseeable future.
Importantly, the agreement went on to mention that thermal storage in district heating would help use the grid to the full.
Finland has been consulting on a similar tiering by size and purpose system with the possibility that data centres above 10MW would be pushed down the queue.
Denmark did it by ranking, the Uk is doing it by pricing. The end result is the same, a reduction in the size of the queue.
How can heat pump installers contribute?
A heat network that services hundreds of buildings needs far less energy than the same buildings on individual heat pumps, mostly because demand across them is diverse a large and efficient enough thermal store can shift that demand. The Warm Homes Plan estimates that the savings of avoided electrical distribution upgrades by 2035 would be between £5 billion and £7 billion. Loads that can wait an hour will beat loads than cannot every time.
Back to the substation
None of this means that connections will be easy, there’s no doubt that the grid is tighter than it was. It’s just not as tight as the queue makes it look. The demand that will connect is a fraction of the capacity that is queueing, the projects that connect will likely draw a fraction of what the book, and reform is shrinking the queue even further.
The load that remains is no bigger than the one that heat pump installers are fitting, street by street.