Sahir Raihan, Structural Engineer and Managing Director, Solar Surveys Ltd, discusses the MCS’s extension of the use of Clause 5.5.5 for flat-roof kits until further notice. Where the clause applies, the installer’s evidence carries significant weight, and MIS 3002 V6.0 specifies the evidence required.
A ballasted array came across my desk recently with everything apparently in order: a mounting manufacturer’s configurator output, a ballast plan, a weight for every tray. On its face it was exactly what a clause 5.5.5 file should contain.
It also had the site on the wrong settings. The configurator had been left on two of its defaults, which it lists itself as values to be checked, and it assumed a friction coefficient of 0.5 between the trays and the membrane with no test report behind it. Corrected for the actual site, the ballast nearly doubled, and that was before the friction coefficient came down to the 0.3 that MIS 3002 requires without a test.
None of that was the manufacturer’s fault, or the installer’s. The software did what it wasasked. But the paperwork looked like evidence, and on its own it was not.
Why clause 5.5.5 matters now
Flat-roof mounting kits, including ballasted systems on roofs of 10 degrees or less, came into MCS 012 with Issue 3.0, and certification became mandatory in 2025. It has proved slow. MCS allowed installers to keep using clause 5.5.5 of MIS 3002 for uncertified flat-roof kits until August 2025, then until November, and in October 2025 extended it until further notice while manufacturers work through certification. At the time of writing, that is still the position.
Clause 5.5.5 was always the route for kits outside MCS 012. What changed is that MIS 3002 V6.0, mandatory since 18 June 2026, expanded it into a list of evidence the MCS contractor must be able to produce:
- that the installation maintains the building’s compliance with the Building Regulations for structural safety, fire safety and weathertightness;
- that a structural assessment and wind loading calculation have been completed for the specific mounting system being installed;
- that the customer has been told to undertake an updated fire risk assessment;
- how the weather-tightness of the roof has been maintained;
- that the system components are compatible with one another;
- and that the system is installed in accordance with the manufacturer’s instructions.
One note in the clause deserves to be read twice. The calculations, it says, do not constitute compliance alone; they must be directly linked to the design and installation of the system. A calculation for a different layout, a different site or a different ballast plan is not evidence for this one.
Getting the wind and sliding case right
For ballasted systems, clause 5.9.13 sets the rules. The pressure coefficients come from BRE Digest 489 or from recognised test data commissioned for the purpose. The wind actions on the site come from BS EN 1991-1-4 and its UK National Annex, and that is where most of the difference between a good calculation and a poor one lies: the site’s basic wind speed, its altitude, the terrain upwind, the height of the building and where on the roof the array sits. Edges and corners carry far more uplift than the middle of a roof, so a ballast plan that is the same weight everywhere should prompt a question.
Sliding is the case people forget. MIS 3002 requires the calculation to use a friction coefficient of 0.3 between the system and the roof unless the actual material combination, slip layer included, has been tested to its Appendix D. The test is simple: a 50 kg mass sits on a plate of one material on a level platform of the other, and a horizontal force is increased until it slides. It is done wet and dry, and the lower result is declared. The calculation must state the coefficient it used, and anything above 0.3 should be backed by the test report. On gravel or green roofs a test value is required, or the array must be mechanically restrained, with a kerb in front of it or tether cables to a fixed point.
So when a configurator output arrives, check three things before you file it: that the site inputs are the site’s, not the software’s defaults; that the friction coefficient is 0.3 or backed by a test report; and that the ballast varies across the roof as the wind zones do.
Can the roof carry it?
The last requirement in clause 5.9.13 has no exceptions: a qualified structural engineer shall be consulted to ensure the roof can withstand the imposed load from both the solar PV system and the proposed ballast. There is no size threshold.
Ballast changes the question. A rail mounted array typically adds 15 to 25 kg/ m² over its footprint. A ballasted system is commonly 30 to 60 kg/m², more on exposed sites or at steeper tilts, and that weight is there permanently, on top of everything the roof was designed to carry. The actual figure depends on the specific system and its manufacturer’s datasheet, and whether a given roof can take it is a question for a project-specific structural assessment.
That assessment covers more than the joists or the deck. It includes the pressure under the trays or rails on the insulation, snow drifting against the array, which acts as an obstruction, and the condition of the roof itself. In our own data, visible condition issues were photographed on 93 per cent of the felt flat roofs we recorded this year. A roof can pass the load check and still not be fit to carry an array for the life of the system.
What to keep on file
For a ballasted flat roof under clause 5.5.5, the file I would want to see holds:
- the wind loading and sliding calculation for this system on this roof, with its inputs stated: wind speed, terrain, building height, roof zones, tilt and friction coefficient;
- the ballast plan, with weights by position, matching that calculation;
- the test report for any friction coefficient above 0.3, and confirmation that the protection layer is compatible with the membrane;
- the structural engineer’s assessment of the roof under the array and its ballast;
- photographs of the ballast as installed, with the method statement and warranty position that show the roof stayed watertight;
- the documents showing the components work together, and the record that the customer was told to update their fire risk assessment.
If the layout changes, the calculation changes with it. That is the line in clause 5.5.5 most likely to catch someone out, and the easiest to stay on the right side of.
Certification for flat-roof kits will catch up. Until it does, the evidence file is the installer’s protection, and the customer’s.